Mini vic.gov.au

This is a low bandwidth version of vic.gov.au. Contents may not be up to date. © Copyright State Government of Victoria

Request for tender

Prepare a request for tender and understand the key components of the documentation.

Purpose of a request for tender

A request for tender (RFT) is a formal, structured invitation to potential contractors to tender or bid for planned construction works. The RFT should allow tenderers to provide information that aligns with the evaluation criteria, enabling you to evaluate responses and select the contractor.

If the procurement process involves a two-staged go-to-market strategy, you will need to develop and evaluate the expression of interest (EOI) before issuing the RFT.

When structuring the RFT document, consider separating key aspects of the document, such as tender conditions, the scope of works and contractual aspects, avoiding unnecessary content crossovers between these sections.

Broadly, the RFT should outline:

Specific information on the project scope and delivery requirements, as well as the draft contractual documents, can then be issued to the relevant disciplines.

The extent of information included within the RFT may be dependent on the project’s size and complexity and selected procurement model. Depending on the capability and capacity of in-house resources, you may wish to engage a consultant to assist in developing the RFT.

Regardless of the complexity of the project, it is recommended that all RFT response requirements are only articulated within the returnable schedules (clearly aligned to the evaluation criteria) and nowhere else throughout the documentation.

You may wish to speak with your OTCD representative about gaining access to standardised RFT documents to help in preparing the tender documentation. Standard conditions of tendering and tender returnable schedules are available for low and medium complexity projects (for use with the Victorian public sector models: AS 4300-1995 General Conditions of Contract for Design and Construct July 2024 and AS 2124-1992 General Conditions of Contract July 2024).

For HVHR projects you will likely require more bespoke advice in the development of the tender documentation. Notwithstanding this, strong precedents exist for most procurement models and can be requested via DTF and OTCD project representatives.

Guidance on the process and requirements for releasing the tender documentation, including tender and forward notices, and evaluating responses is available.

Open all

Project overview and tender requirements

You should provide tenderers with a high-level summary of the project and the requirements for tender submissions, as well as associated timeframes for both tender submission and project delivery. This will allow tenderers to quickly identify whether the opportunity is aligned to their organisation’s strengths and interests as well as capacity to deliver the project.

The opportunity, tender process and key timeframes

You will need to provide tenderers with an overview of the project. For business-as-usual projects this may involve:

Project scope summary and commercial arrangements

You will need to provide tenderers with an overview of the project’s scope and commercial arrangement. For business-as-usual projects, this may simply involve outlining the project’s scope and the general commercial arrangement under which you propose to contract.

For more complex projects, you may also wish to:

Summary of the tender process

You will need to provide tenderers with an overview of the tender process. The level of detail contained within this section will vary depending on the project’s size and complexity. Broadly, it should seek to:

Returnable schedules

As part of the RFT, you should include returnable schedules aligned to the evaluationcriteria and reflective of the information you have asked tenderers to provide throughout the RFT. In addition to these returnable schedules, you may also wish to ask tenderers:

Functional requirements

Typically, you will need to provide tenderers with an outline of the project’s functional requirements. The functional requirements, sometimes called user requirements, will vary depending on the project’s specifics as well as the procurement model.

Technical requirements

You should provide tenderers with an outline of what must be addressed in relation to the architectural and technical requirements. Technical specifications will vary significantly depending on the selected procurement model, such as differing output specification vs input specification requirements. If the procurement model does not involve a design component (i.e. construct only), then you should provide the detailed design and other design specifications to the tenderers as part of this section.

Broadly this section should outline:

Ongoing service requirements

If the project involves procuring an ongoing component or service post-commissioning during its operations phase, you will need to outline these specific ongoing requirements in the tender, for example the provision of on-site practical training in the operation and/or maintenance of equipment. It may also be relevant to the installation and maintenance of specific specialist equipment. This is typically only relevant for complex projects with alternative procurement models that involve private sector collaboration.

The RFT should include draft contract documents detailing the commercial arrangements under which the contractor will deliver the works. The form of contract required will vary significantly depending on the chosen procurement model. Depending on the project’s size and complexity, you may wish to engage legal advisors to assist in drafting the contract documentation.

Construction contracts must be to be in a form approved by the Secretary to the Department of Treasury and Finance (DTF). These contracts are referred to as the Victorian Public Construction Contracts. For most low and medium complexity projects this may be a construct-only tender approach where the Victorian public sector model AS 2124-1992 general conditions of contract will be applicable. Where a design and construct procurement approach has been selected, the Victorian public sector model AS 4300-1995 general conditions of contract may be applicable. The OTCD can also advise where ’time is of the essence’ and other special forms of contract may be advisable.

If you are approaching selected tenderers off a preferred supplier panel, you may need to comply with standard terms and conditions when engaging contractors.

Further guidance on contracting requirements, as well as Victorian Public Construction Contracts that you may wish to leverage (depending on the chosen procurement model) for minor and major works, is available.

I need to:

Education & training

Updated 31 December 2025



About the VIC Government

Grants and programs

Jobs and careers

Arts, culture and heritage

Business and the workplace

Communities

Education and training

Environment, water and energy

Finance and economy

Health and social support

Housing and property

Law and justice

Safety and emergencies

Science and technology

Sport and recreation

Traffic and transport

Working in the Victorian Government