Managing the program

Learn about the importance of managing a program and find guidance on monitoring and control, to ensure the project remains on-program during the delivery phase and is successfully delivered on time. A well developed and clearly articulated program is essential for ensuring the project is completed on time, all project activities are planned appropriately and communicated to the appropriate parties. The program will allow you to understand the interdependencies between activities and determine the order in which activities must be completed to ensure the project is delivered on time.

It is important to note that the TAFE may need to develop various programs or make a number of revisions to the program, throughout the project lifecycle, including for internal processes such as obtaining the necessary funding and approvals, procurement, and managing the design process and the works. You will need to agree on the program for the delivery of the works with the contractor.

The need to manage the program

Delays to the program may prevent the project from being completed on time, within the required budget and/or to the required standard. This may impact the realisation of project benefits envisaged during the project definition, funding and approvals phase. It is therefore important to plan, schedule, monitor and control the program.

The program is also an important tool during delivery to help:

It is also important for the program to be up to date and accurate to assess EOT claims and other impacts caused by change events.

Open all

Step 1: Planning

This step involves understanding important dates, time constraints and key milestones which the project is required to meet.

Every project has a start and an end date. These dates may be linked to a critical constraint, such as a government commitment to have a project completed by a certain date or a critical interdependency with another important project. In some cases, these dates are arbitrarily established by the project team.

In the project’s early stages, when the project need is established, you may need to identify critical dates. These may include:

Step 2: Scheduling

Once the scope is defined, quality requirements and project risks determined, and an estimate of activity duration in place, you should undertake the scheduling process. This will typically occur after funding has been received and project definition has been completed, during the project definition, funding and approvals phase.

During the scheduling process, you will need to develop a program to illustrate how project tasks will be sequenced and activities will be allocated between different stakeholders (for example, different works to be completed by different consultants, contractors or trades). The program is typically in the form of a Gantt chart.

The concept of a Gantt chart is to map out which tasks can be done in parallel and which tasks should be done sequentially. A Gantt chart displays information visually, in a clear, easy-to-understand way and is used to:

Step 3: Monitoring

Monitoring is important for determining if the program is running as planned and deciding when changes or intervening corrective action (for example, rescheduling or accelerating the works) may be required.

Once the project program has been set, monitoring includes analysis of past events, recognition of trends and assessment of the potential impacts on the future schedule - comparing what actually happens during the project against what was expected to happen under the project schedule.

Monitoring includes the communication and reporting of findings to the wider project team.

Monitoring is an ongoing activity and may include processes such as:

Step 4: Controlling

Controlling the program ensures that the objectives of the project are met in accordance with the program and aims to achieve the timely and successful completion of the project.

Controlling the program may include the following processes:

The critical path is the longest sequence of dependent activities within a program, which must be completed on time for the total project to complete on time.

Activity on the critical path cannot be started until its predecessor activity is complete. In other words, if activity on the critical path is delayed for a day, the entire project will be delayed for a day unless a following activity is completed a day earlier.

The purpose of understanding the project’s critical path(s) is to be able to focus effort in managing the activities that lie on that critical path. If all the critical path activities are completed on time and there is no slippage on other activities (which are not on the critical path past the anticipated end date), the whole project will finish on time.

Understanding the project’s critical path will also help with the assessment of contractor extension of time (EOT) claims, as well as any other unforeseen events which may impact the project. If an EOT claim arises or an unforeseen event occurs, you will be able to consider opportunities to reschedule activities or accelerate some works to maintain the critical path (if the date for practical completion is impacted). If an EOT is genuine, the contract will set out the mechanisms for relief from elements such as liquidated damages.

During the procurement phase, you are likely to require tenderers to return a proposed program as part of their tender response.

In order to ensure you receive an acceptable program from tenderers, the tender documentation should clearly identify critical dates within the program. Tenderers must then incorporate these critical dates into their program and sequence of work.

You should evaluate tenderers’ proposed programs contained within their tender responses. This includes ensuring critical dates, as well as any constraints and interdependencies, are appropriately considered.

You should agree on the successful tenderer’s key dates and milestones, prior to engaging the contractor, so they can be included in the signed contract. You should also:

Once the contractor is engaged you should monitor actual progress against the forecast delivery program to ensure that the project achieves its objectives in line with any time constraints.

In practice, on at least a monthly basis, you should perform the following tasks to ensure that the contractor’s program status reporting is as accurate as possible:

To ensure timely completion of the project during delivery, the TAFE may take the following actions:

I need to:

Education & training

Updated 17 September 2024



About the VIC Government

Grants and programs

Jobs and careers

Arts, culture and heritage

Business and the workplace

Communities

Education and training

Environment, water and energy

Finance and economy

Health and social support

Housing and property

Law and justice

Safety and emergencies

Science and technology

Sport and recreation

Traffic and transport

Working in the Victorian Government